Selecting properties

Prioritizing and Phasing Projects

Picking the right buildings isn't just a financial exercise — it's a strategic one. The temptation is to start with the easiest property. Resist it. ELACC deliberately chose both a large LIHTC building (Lorena Terrace, newer and more complex) and a small 100-year-old NOAH building (Vallejo) for their first two projects. Different building types, different challenges, different lessons. Picking the buildings that teach you the most is as important as picking the ones most likely to succeed. Three main factors should guide your prioritization:

  1. Urgency: How quickly does the building need repairs or energy upgrades?

  2. Readiness: Is the building in a good place to start work now? Financially, physically, and operationally?

  3. Learning opportunity: Choose a building or mix of buildings that may help your team learn more. Do not just pick the easy ones. Evaluate new approaches and prepare for larger projects later.

Before deciding which properties to decarbonize, you’ll need to assess each building’s physical condition, financial readiness, and the needs of its tenants. This helps you use your time and money wisely and supports better learning across your portfolio. Use Property Evaluation Matrix (Appendix S4-A1) to complete an assessment of your portfolio and set your priorities.

After completing the evaluation of your portfolio, carefully consider which properties to decarbonize. Use the following questions to guide you in completing your Property Selection (Appendix S4-A2).

Which properties will help us learn the most?

Select a mix of easy and challenging properties to maximize learning outcomes. More complex properties can offer opportunities to solve challenging issues that will benefit future projects.

How many properties can we oversee at one time?

Evaluate your team's capacity to manage multiple projects at once. Consider resources like staff availability, interns, contractor schedules, and funding limits to determine how many properties can be retrofitted simultaneously.

What is the physical condition of the building?

Older buildings may have unique needs compared to newer ones. Differences in building age, number of units, and existing infrastructure (e.g., HVAC systems, water heating) will impact the complexity of a project.

What is the current level of tenant engagement at each property?

Engaging tenants involves building communication and trust. Buildings at which engagement is low will require more effort, which may make the decarbonization more difficult.

Why are we interested in decarbonizing?

Consider whether you are aiming to achieve a green building certification, improve the building’s GRESB score, respond to investor pressure, or address any marketing goals. Determining where your priorities lie will help you select the most appropriate building to decarbonize.

Financial & Organizational Impact Analysis

It is crucial that you understand how each property you select will affect your finances. Before making your final decision follow these steps:

  • Evaluate the expected changes in energy costs for both landlords and tenants.
  • Assess potential impacts on utility allowances.
  • Review any changes in repair and maintenance expenses.
  • Identify available incentives, including their timing and amounts.
  • Consider potential rent increases or the ability to pass through capital costs.
  • Consider debt service requirements.

Equally important to account for are rent impact restrictions, tenant cost protections, long-term affordability goals, and non-energy benefits that address other community or property needs.

One risk deserves plain language: fuel switching can raise operating costs. In California today, gas is often cheaper per unit of heat than electricity, so an all-electric building can see higher utility bills even as it uses less energy overall, particularly where the owner pays utilities. Model post-retrofit utility costs honestly (on-site solar, as at Lorena Terrace, can offset much of the increase) and build the answer into your utility allowance and underwriting assumptions rather than discovering it after conversion.

Properties selected, the work now shifts from buildings to people: the tenants who live in them.