conducting quality assurance and verification
This stage verifies that installed systems operate as intended, comply with program requirements, are properly maintained, and meet tenant expectations. Follow the steps below to help safeguard incentives and proactively address any post-installation tenant concerns.
-
Plan and Schedule Inspections
- Coordinate inspections with incentive program implementers, city officials, and required parties.
- Ensure all systems and installations are accessible for inspections, and keep tenants informed about inspection timelines.
-
Perform Commissioning
- Commission systems to verify that all new equipment operates as intended and meets performance benchmarks.
- Identify and resolve any discrepancies or installation errors during this phase.
- Some incentive programs provide their own commissioning software or tools, use them to verify system performance.
-
Verify Equipment Performance
- Confirm that all installed equipment (e.g., heat pumps, water heaters) operates efficiently and meets expected performance levels.
- Use data logging tools or commissioning reports to verify performance metrics.
-
Document Completed Work
- Detailed installation records.
- Photos of installed systems.
- Specifications for each piece of equipment.
- Copies of inspection reports and compliance certificates.
- Use a centralized document repository for easy access during audits or follow-ups (see Document Repository Appendix S10-A1).
-
Obtain Necessary Certifications
- Collect all required certifications for regulatory compliance and incentive program approvals.
- Ensure certifications are filed and readily accessible for audits or inspections.
-
Train Maintenance Teams
- Provide training for maintenance staff on the operation, troubleshooting, and upkeep of new systems. The installer is the best trainer: have the contractor run these sessions before handoff (for example, descaling heat pump water heaters in hard-water areas).
- Include resources like manuals, warranty documents, and a list of spare parts for future needs.
-
Tenant Education
- Provide instructional videos, user manuals, and tenant guides for new systems.
- Focus training on how the new equipment differs from the old: ELACC found that the few tenants reporting higher bills were switching mini-splits on and off like old window units instead of holding a set temperature.
- Remind tenants that systems cannot be altered and that an inspection will be conducted in the future.
-
Conduct Post-Retrofit Inspections
- Perform periodic inspections, such as semi-annual check-ups, to ensure systems continue to function as intended (see table below).
- Address any emerging issues promptly and document actions taken.
| Task | Details | Responsible Party | Timeline |
|---|---|---|---|
| Inspect installed systems | Confirm equipment is operational | Maintenance Team | Every 6 months |
| Verify Performance Metrics | Ensure equipment meets efficiency goals | Technical Consultant | During Inspection |
| Address Tenant Concerns | Collect tenant feedback on performance | Property Manager | Ongoing |
| Update Documentation | Log inspection results and actions taken | Maintenance Staff | After inspections |
With systems verified and documented, Section 11 turns to whether the retrofit delivers the savings it promised.