At this stage, it’s time to review the information you have gathered and begin to thoughtfully plan for the necessary upgrades. Work with your decarbonization engineer to look closely at the building’s existing systems and decide what should be replaced or improved. Create a Scope of Work (SOW) that meets the building’s needs, aligns with available funding, and includes plans for electrical and infrastructure upgrades needed to support new equipment.

As you consider which new technologies to implement, be sure to factor in costs, timelines, program requirements, and compliance obligations. Through the Comprehensive Affordable Multifamily Retrofit Program (CAMR), you can receive free technical assistance to help shape your SOW, confirm which upgrades qualify for incentives, and make sure your plan meets code and program requirements. Below are the key steps in developing your scope of work.

Data Collection & Review

Use the information you gathered to take a closer look at the infrastructure and utility usage of the building you selected. Take note of what information is missing and what your decarbonization engineer recommends.

Conducting a Site Visit

Understand what you are looking for and what is necessary prior to performing a site visit. Complete a walk-through of the building you plan to decarbonize to fill in the gaps in your information and determine the feasibility of your project. Pay special attention to whether there are any structural and/or design limitations.

Be aware that you will need your maintenance team to access some sections of your checklist (transformers, HVAC units, panel boxes, etc.). Bring the necessary tools: a tape measure for insulation, screwdrivers for panel boxes, and a flashlight. Be sure to take photos of everything so that you can double-check information later.

We recommend completing the next step simultaneously.

Assessing Electrical Capacity and Plumbing Infrastructure and Planning for or Avoiding Upgrades

Complete the Electrification Feasibility Assessment (Appendix S6-A1), a tool we adapted from AEA (2021) to evaluate a building’s electrical infrastructure. You want to determine whether the building can handle the additional load of new technologies (such as electric heating systems or induction stoves). If upgrades are needed, include them in the project scope to avoid delays or compliance issues.

Along with electrical capacity, it is important to understand whether the existing plumbing system can support new heat pump water heaters or other electrified equipment. Older buildings may have aging pipes, limited hot water distribution, or insufficient drainage that can affect installation. Assess pipe sizing, venting, and water pressure, and identify any repairs or upgrades needed to safely support new systems. If plumbing improvements are required, include them in the project scope early to avoid construction delays, added costs, or code compliance issues.

Pre-bid due diligence starts here, about six months before construction: benchmarking, electrical load confirmation, environmental and structural testing for pre-1980 buildings, fire-rating assessment, and logistics mapping. Section 9 (Pre-Construction Planning) covers the full checklist.

Two practices belong in scope development itself. Require every bidding contractor to walk the site before bidding: no two units or properties are identical, and a contractor who has seen existing conditions firsthand gives a far more accurate cost. Use the same visit to capture date-stamped pre-construction photos of water heaters and AC units (brand, model, and serial-number views, with pulled-back shots), which incentive programs require to close out and pay.

Defining Your Scope of Work

Work with your decarbonization engineer or consultant to create a Scope of Work (SOW) that clearly outlines the energy efficiency measures, equipment specifications, and code requirements for your project. A well-prepared SOW helps prevent delays, supports accurate budgeting, and makes it easier to apply for incentives and grants. See an example of a scope of work here: Sample SOW (Appendix S6-A2).

When developing your SOW, make sure the proposed equipment will work for your building. New electric systems, especially heat pumps and heat pump water heaters, can be larger, heavier, or shaped differently than the equipment they replace. Compare the size, weight, and form factor of the new equipment to what currently exists. Confirm there is adequate space, structure, and electrical capacity. Equipment options also improve quickly: lower-power-draw induction ranges now on the market can avoid panel upgrades that were unavoidable when ELACC started, so ask your engineer about current options before assuming an electrical upgrade is required.

Consider installation details such as ducting, electrical routing, and any fire or building code requirements. Think through the placement of equipment from a tenant perspective as well. For example, some outdoor units may look like they could sit on a patio but may be too heavy to pass structural or code requirements. These issues should be resolved during the SOW stage, so they do not create surprises during construction. Also, certain refrigerants used in older heat pump models are banned in Los Angeles. Your engineer should confirm that all proposed equipment complies with local refrigerant rules and current code standards.

Refining Your Scope of Work

To complete this step, you will need to have received bids and selected a contractor (discussed in the following section). Work with your decarbonization engineer and contractor to confirm that the scope of work meets local building codes and regulations. Retrofit projects often need to comply with energy and water efficiency laws, which may dictate the implementation of specific measures (e.g., low-flow fixtures). Additionally, if you have a limited budget consider reusing certain materials (e.g., existing wiring) or selecting alternatives for high-cost items. Your contractor can help you identify areas where costs can be reduced, while your decarbonization engineer can help verify that these changes meet program requirements.

Lastly, if new technologies or systems increase the building’s energy demand, ensure that these changes (e.g., wiring or panel upgrades) are included in your SOW. Once you have a comprehensive SOW you can begin to plan for construction.

A complete scope of work is also your main tool for the next step: putting the project out to bid.