Selecting a contractor

Choosing the right contractor is one of the highest-leverage decisions in the whole project. The wrong contractor creates change orders, missed inspections, frustrated tenants, and lost incentives. The right one moves the schedule forward, communicates proactively, and leaves your maintenance team with the training and documentation to sustain the work. Take this step seriously.

Identifying the Right Contractor

There are three major types of contractors you can select from; the following table provides an overview of each.

Table S7-T1: Contractor Overview
Contractor TypeDescriptionProsCons
General ContractorManages the full scope, coordinating subcontractors and schedules.Comprehensive management, one main point of contactMay lack expertise in specialized retrofit tasks
Specialist ContractorExperts in specific areas, such as HVAC or electrical retrofits.Expert knowledge in specific retrofit tasksMay require additional coordination and oversight
Construction ManagerProvides oversight throughout all project phases, useful for complex retrofits requiring coordination across multiple teams.Continuous oversight and streamlined managementAdded cost for management services

Use the following questions to guide your search for and selection of a contractor.

Can we leverage existing relationships for referrals?

Consider asking partners, such as AEA, for recommendations or referrals to contractors who have worked successfully on similar projects.

Does the contractor have experience with energy-efficient retrofits?

Seek contractors who understand the specific requirements of green retrofits, as this experience is critical for ensuring successful implementation.

How can we align contractor capabilities with our project’s needs?

Ensure selected contractors are well-versed in the specific technologies and equipment planned for the retrofit, such as energy-efficient HVAC systems or induction cooktops.

Does the contractor possess the necessary certifications?

One way to check a contractor license is through the following website: www.cslb.ca.gov

Request for Proposals

Send the finalized SOW to potential contractors. Aim to receive at least three bids to ensure competitive pricing and adequate coverage of the scope of work. Compare bids beyond just cost; look at scope, lead times, and contractor flexibility. State prevailing-wage and apprenticeship requirements in the RFP itself: larger jobs with significant electrical scopes typically trigger them, and ELACC now splits work into separate prevailing-wage and non-prevailing-wage contracts, sometimes with the same general contractor. AEA can help level bids and evaluate constructability.

Evaluating Contractor Quality

Contractor performance varies more in occupied rehabilitation than in standard construction — occupied rehab adds complexity that separates experienced contractors from everyone else. ELACC and its Retrofit.LA cohort partners have seen directly how contractor choice shapes cost, schedule, and quality. When reviewing bids, weight these criteria:

Clarity of Bids & Contracts

Prioritize contractors who clearly outline scope, assumptions, responsibilities, and exclusions.

O&M Training & Closeout Materials

Stronger contractors deliver organized O&M manuals, warranty information, and staff training. Weaker contractors provide minimal or unclear materials, creating long-term maintenance issues.

Responsiveness to Defects & Warranty Issues

Choose contractors who respond quickly to punch list items and have defined response timelines.

Communication Quality

Consistent communication is essential, especially with tenants involved. Put high importance on contractors that include a communication plan and an identified project manager or key team member responsible.

Two further criteria proved decisive in partner projects:

Occupied-rehab track record

Require proven experience managing tenants safely in occupied units (not just vacant rehab), and ask the contractor to prove it with references and completed projects. ELACC also prioritized contractors comfortable working with vulnerable residents and willing to go the extra mile.

Financial stability

Incentive programs are slow to reimburse, so the contractor must be able to float costs and wait for payment. Confirm how much they can carry and for how long. A contractor carrying multiple trades with their own staff can also resolve defects and warranty issues faster.

How Partners Approached Contractor Selection

ELACCEsperanzaLTSC
Procurement processRFP, with equipment specs + AEA supportNo RFP, sent equipment specs from AEATBC
Distribution listExisting relationships, ended up selecting one of 2 responsive bidders (3rd did not respond)Existing relationships, ended up getting referral from AEATBC
Contractor criteriaTBCTBCTBC
Contractor “type” selectedLocal, experienced, flexible on timing of payment, willing to work with + wait for incentivesLocal, inexperienced, flexible on timing of payment, willing to work with + wait for incentivesSpecialized Decarb Contractor, Sophisticated, Local
Started with a non-local firm that did not perform well but was Specialized and Sophisticated

TBC = to be confirmed.

Select Equipment and Finalize Placement

Finalize equipment specifications to meet incentive program guidelines and ensure optimal placement for tenant convenience. This includes specifying whether equipment is intended for indoor or outdoor installation. Establishing clear equipment standards helps ensure eligibility, avoids costly rework, and protects incentive value. Work with the contractor to confirm that the building’s infrastructure can support new equipment placements and plan for lead times to avoid delays. Taking the time to document and communicate these standards upfront helps prevent costly delays or reductions in incentive payouts and supports more effective project planning. For example, see the case study below.

Construction Phasing and Scheduling

Plan the construction timeline in a way that reduces disruptions for tenants. This often means completing the work unit-by-unit or area-by-area so people can stay safely in their homes. Make sure the schedule also lines up with your funding and incentive timelines, which can help lower costs, especially costs related to construction interest.

Construction Budget and Incentive Draw Schedule

Create a budget that includes all construction costs and shows when you expect to receive incentive payments. This helps you stay on track financially and plan for when funds will arrive.

Expected Permits and Inspections

Before starting work, make sure you complete all required permits and registrations. Typical steps include:

  1. Register with the Affordable Housing Liaison Unit (AHLU) at the Mayor’s office.They can help guide you through the permitting process once you have a basic idea of your project.
  2. Register the property on LADBS.org.The Los Angeles Department of Building and Safety is responsible for building permits and inspections.
  3. Coordinate with LADWPFor any electrical service upgrades, meter work, or program requirements.
  4. Complete a Tenant Habitability Plan with LAHDTo ensure tenants are protected and informed during construction.

Permitting timelines range from six weeks for over-the-counter permits to six months or more when LADWP service upgrades are involved, and they often dictate the master construction schedule. Engage the utility as early as possible and align permits with your incentive deadlines; Section 9 (Permitting Timelines) provides a working guide.

With a contractor selected and a schedule taking shape, Section 8 covers assembling the financing that carries the project into construction.